Thursday, November 29, 2012

Building Update

Just a quick one with some photos and my pre-plaster inspection report. 

Things are progressing well, I have been very happy with Jason Smith my SS, he even went to Bali for a week, but had another guy taking care of me - and all was organized and smooth. 

Chatting with a few of the tradies, I have had more than one tell me he is the best Carlisle SS  - always organized - they're never waiting on stuff. 

The Brickies should be done this week, staircase in and the painters will be in over the Christmas break apparently. 

Looking like an end of Feb move in :)

Any way here is the latest inspection report - (all was taken care of promptly), and some progress photos from the last month. 



Brickies getting started

Rear of house

The brickies at work, you can also see our really ugly front doors, we  couldn't get the ones we wanted, so we got the base level doors and will replace them after handover

Brickie Progress

Plaster has been hung

From the living room to the kitchen

The alfresco

The girls bathroom

Saturday, November 3, 2012

Framing Inspection Completed

Things are still progressing nicely.

I had my frame inspection completed with New home Inspections, it went well with some defects noted:

My Inspection Report

I have spoken with my Carlisle Site Supervisor, he has said that all defects other than the slab have been corrected. The slab correction is scheduled however. I will be having New Home Inspections do a pre-plaster inspection, they will review all remedial work at that time.

Anyway enjoy some more photos.

Framing Complete

Framing Complete

One week later the roof is on and the roughing in has begun

Front of the house with my new sexy roof

From the back